Tasks & Rectification Items
7 of 11 complete-
✓Done ›
Completed 4 Sep 2024 · EBS Fire Engineering
Following receipt of the Fire Order on 12 Aug 2024, the committee sought quotes from fire engineering consultants. EBS was selected based on their prior knowledge of the building from the 2022 AFSS.Documents- 📋 EBS Scope of Works Report — 4 Sep 2024
- 📄 Fire Order FO-2024-0381 — NSW Fire & Rescue, 12 Aug 2024
-
✓Done ›
Completed 22 Oct 2024 · Sparkline Electrical
14 emergency/exit light fittings on Levels 2 and 3 failed the 90-minute discharge test. Sparkline replaced all 14 with LED emergency batten fittings (IP-rated). EBS inspected and confirmed compliance on 29 Oct 2024.Documents- 🧾 Sparkline Invoice SPARK-1104 — $4,840 · Paid
-
✓Done ›
Completed 14 Nov 2024 · QFD Doorworks (contractor)
4 fire doors in basement levels B1 and B2 were found to be non-compliant: incorrect gap tolerances, failed intumescent seals, and non-closing mechanisms. All 4 doors re-hung and recertified under AS 1905.1. -
✓Done ›
Completed 30 Nov 2024 · Hydropressure Services
-
✓Done ›
Completed 18 Jan 2025
Quotes received- 💰 EBS Quote — $74,500 incl. GST (does not include commissioning)
- 💰 AED Quote — $61,200 incl. GST (includes commissioning) ✓ accepted
- 💰 Incode Quote — $68,400 incl. GST (does not include commissioning)
-
✓Done ›
EGM held 12 Feb 2025 · 34 in favour, 4 against, 2 abstained
Documents- 📝 EGM Notice & Agenda — circulated 29 Jan 2025
- 📝 EGM Minutes — issued 19 Feb 2025
-
✓Done ›
Completed 21 Feb 2025
Documents- 📑 AED Contract — Sprinkler Upgrade — executed 21 Feb 2025, $61,200 fixed price
- 📧 EBS Recommendation Letter — Matthew, 24 Feb 2025
-
→Active ›Overall progress35%Commenced 3 Mar 2025 · Est. completion 2 May 2025Work stages
-
✓Mobilisation & site establishmentAED · 3 Mar
-
✓Pump set delivery & inspectionAED · 7 Mar
-
→Plantroom pipework rough-inAED · in prog.
-
Basement distribution pipeworkAED · est. Apr
-
Sprinkler head installation — all floorsAED · est. Apr
-
Hydraulic pressure testingAED · est. late Apr
-
Commissioning — EBS witnessAED + EBS · est. May
-
EBS fire engineer's certificate issuedEBS Johnny · est. May
Open items⚠ Variation pending approval
EBS requested an additional isolation valve in B2 (est. $680). Awaiting committee sign-off. View variation →Key contacts for this task📋 Superintendent: EBS — Johnny🔧 Contractor PM: AED — Karen Bell🔧 Site super: AED — Dave Nguyen🏢 Strata Manager: Charles CristSite diary19 Mar 2025Plantroom pipework approx. 60% complete. Pump set in position, not yet connected. No access issues reported.14 Mar 2025Noise complaint received from Unit 7 re early morning works. Charles confirmed permitted hours 7am–5pm Mon–Fri with AED.11 Mar 2025EBS issued variation request — additional isolation valve required at B2 junction per hydraulic design review. Est. $680 + GST.6 Mar 2025Commencement walkthrough completed. EBS (Matthew), AED site team, Charles Crist. Minor access issue at plantroom hatch — AED to liaise with building manager.3 Mar 2025AED mobilised on site. Equipment delivered. Notice posted to all residents.Related communications19 Mar 2025AED site supervisor — progress update on plantroom pipework11 Mar 2025EBS (Johnny) — variation request re: additional isolation valve in B26 Mar 2025On-site meeting: AED, EBS (Matthew), strata manager — commencement walkthroughDocuments- 📑 AED Contract — Sprinkler Upgrade — executed 21 Feb 2025, $61,200 fixed price
- 🧾 AED Progress Claim 1 (mobilisation) — $14,000 · Paid 10 Mar 2025
- 🔧 EBS Variation — B2 Isolation Valve — est. $680 · pending approval
- 📋 AED Construction Programme — issued 25 Feb 2025
-
-
→Scheduled ›
Incode Fire engaged Feb 2025 · Site visit 28 Mar 2025
Incode to audit all 22 fire doors on Levels 1–6 against AS 1905.1. Report expected within 10 business days of inspection. -
Pending ›
Estimated May 2025. Dependent on AED completing installation works.
-
Pending ›
Cannot proceed until EBS fire engineer's certificate issued and Incode door audit complete.
Communication Log
34 entries19 Mar 2025
AED site supervisor — progress update on plantroom pipework
Charles Crist → AED (Dave Nguyen) · Initiated by: Strata Manager
Morning
17 Mar 2025
Incode — confirmed 28 Mar site visit for fire door audit, access arrangements
Incode → Charles Crist · Initiated by: Incode
Afternoon
11 Mar 2025
EBS (Johnny) — variation request re: additional isolation valve in B2
EBS Johnny → Charles Crist · Initiated by: EBS
Morning
6 Mar 2025
On-site meeting: AED, EBS (Matthew), strata manager — commencement of works walkthrough
AED + EBS Matthew + Charles Crist
Morning
24 Feb 2025
EBS (Matthew) — issued formal recommendation letter endorsing AED quote
EBS Matthew → Charles Crist · Initiated by: Strata Manager (requested)
Afternoon
12 Feb 2025
EGM held on-site — special levy resolution passed, AED contract authorised
Owners Corporation (34 lots present/proxied) + Charles Crist
Evening
29 Jan 2025
EBS (Johnny) — clarification on scope: AED quote includes commissioning, Incode does not
Charles Crist → EBS Johnny · Initiated by: Strata Manager
Afternoon
18 Jan 2025
Committee meeting — three quotes tabled, EBS recommendation discussed, EGM date set
Committee + Charles Crist
Evening
14 Jan 2025
Incode — quote for sprinkler upgrade submitted ($68,400 incl. GST)
Incode → Charles Crist · Initiated by: Incode
Morning
9 Jan 2025
AED — quote for sprinkler upgrade submitted ($61,200 incl. GST, incl. commissioning)
AED → Charles Crist · Initiated by: AED
Afternoon
Budget & Invoices
Approved Budget
$92,800
Paid to Date
$28,560
Pending / Contracted
$61,200
| Invoice / Ref | Supplier | Description | Date | Amount | Status |
|---|---|---|---|---|---|
| EBS-2024-0912 | EBS | Scope of works report & fire engineer consultation | 30 Sep 2024 | $3,300 | Paid |
| SPARK-1104 | Sparkline Elec. | Exit & emergency lighting replacement — L2 & L3 | 28 Oct 2024 | $4,840 | Paid |
| EBS-2024-1122 | EBS | Fire door remediation certification | 20 Nov 2024 | $1,650 | Paid |
| HYDRO-0071 | Hydropressure | Hose reel pressure test & Level 4 reel replacement | 5 Dec 2024 | $2,970 | Paid |
| EBS-2025-0203 | EBS | Quote preparation & tender assessment | 3 Feb 2025 | $1,800 | Paid |
| AED-2025-0047 | AED | Sprinkler upgrade — progress claim 1 (mobilisation) | 10 Mar 2025 | $14,000 | Paid |
| AED-2025-0061 | AED | Sprinkler upgrade — progress claim 2 (pipework) | Due ~15 Apr 2025 | $22,000 | Pending |
| AED-2025-0062 | AED | Sprinkler upgrade — final claim (commissioning) | Due ~15 May 2025 | $25,200 | Forecast |
| EBS-2025-COMM | EBS | Commissioning witness & fire engineer certificate | Due ~May 2025 | $2,200 | Forecast |
| INCODE-2025-XX | Incode | Fire door audit — Levels 1–6 | Due ~Apr 2025 | $11,800 | Forecast |
Resolutions & Decisions
Carried (ordinary resolution): That the Owners Corporation approve a special levy of $1,850 per unit entitlement, payable in two instalments: 50% by 28 Feb 2025 and 50% by 30 Apr 2025. 34 in favour, 4 against, 2 abstained.
Carried (ordinary resolution): That the Strata Manager be authorised to execute a contract with AED Fire Protection at $61,200 incl. GST. Unanimous.
Carried (ordinary resolution): That EBS Fire Engineering be retained as superintendent/certifier at a cost not exceeding $4,000 incl. GST. Unanimous.
Committee decision: To call an EGM for 12 Feb 2025. Three comparative quotes to be circulated to all owners by 31 Jan 2025.
Owner Comments
via owner portalMR
M. Reynolds
Unit 12
20 Mar 2025
When is the second levy instalment due? I haven't seen a notice come through yet for the April payment.
PL
Unit 7
15 Mar 2025
There's been a lot of noise from the plantroom during the works, especially early mornings. Can we get confirmation of the permitted hours?
SW
Unit 21
14 Feb 2025
Happy with how this has been handled. Good to see three quotes obtained and the committee making a considered decision.
TK
Unit 3
30 Jan 2025
Why is the AED quote $7,200 cheaper than Incode? Is there something different in what's included? I'd like this clarified before the EGM.
Status Snapshot
Compliance deadline
30 Jun 2025
Days remaining
95
Works on track
Yes
Open variations
1
Overdue invoices
None
Action needed: EBS variation (isolation valve, est. $680) awaiting committee approval.
External Providers
EBS Fire Engineering
Lead fire engineer · Superintendent · Certifier
- Johnny — Principal Engineer · johnny@ebsfire.com.au
- Matthew — Project Engineer · matthew@ebsfire.com.au
- Office: (02) 9234 5600
AED Fire Protection
Contractor — sprinkler upgrade (engaged)
- Site supervisor: Dave Nguyen
- Karen Bell (PM) · kbell@aedfire.com.au
- Office: (02) 8811 2200